COOEC wins $800m Qatar offshore contract
Takeaways
- QatarEnergy awarded COOEC a QR2.9 billion ($800 million) contract.
- The package covers more than 100 km of subsea infrastructure.
- The project supports redevelopment of the Maydan Mahzam offshore oil field.
- The full contract period is 66 months.
- The scope includes subsea pipelines, power cables and umbilicals.

Zawya
COOEC Qatar work will proceed under a QR2.9 billion ($800 million) EPIC contract awarded by QatarEnergy to Offshore Oil Engineering Company. The package covers offshore installation of more than 100 km of subsea pipelines, power cables and umbilicals for the redevelopment of the Maydan Mahzam offshore oil field.
The contract is titled EPIC2-MM Subsea Pipeline, Power Cables & Umbilicals, also identified as MM-EPIC2. Its scope includes EPC work together with the installation of the subsea infrastructure, according to a statement from COOEC.
The award forms part of QatarEnergy’s redevelopment programme for the Maydan Mahzam offshore oil field. The project is located offshore Qatar, and the published information did not provide further details on the field redevelopment beyond the contract package.
The full contract period is 66 months. The information published did not state when work would begin or when the installation would be completed, and it did not set out a schedule for the individual workstreams.
The subsea package includes pipelines, power cables and umbilicals. The published information did not identify other companies involved in the package or break out separate values for the engineering, procurement, construction and installation activities.
COOEC is described in the source as a leading Chinese group. The contract value was reported in both Qatari riyals and US dollars, with no separate figures given for the individual components of the work.
Questions
What is the value of the COOEC Qatar contract?
The COOEC Qatar contract is worth QR2.9 billion, equivalent to $800 million.
Who awarded the offshore contract to COOEC?
QatarEnergy awarded the offshore contract to Offshore Oil Engineering Company, known as COOEC.
How long is the COOEC Qatar contract?
The full contract period for the COOEC Qatar project is 66 months.
Source: Zawya